Kitchen renovation checklist

The room with the most trades, the longest lead times and the least room for a late change of mind.

What goes wrong in a kitchen

  • AvoidOrdering the units before the room is measured after plastering. Carcass runs are unforgiving and a 15mm error shows.
  • AvoidTemplating the worktop too early. The units have to be fitted and level first, or a stone worktop gets recut at your expense.
  • AvoidMoving a socket or a waste after the plasterer has been. Chasing a finished wall means patching, drying and repainting.
  • AvoidBooking a fitting week before appliance lead times are confirmed. The model you chose may not be in stock when you need it.

Phase 01

Decide before anyone starts

These decisions all constrain the trades that follow, so making them late is what pushes a kitchen over budget.

Phase 02

Strip out

Get the room back to a shell before any new work starts.

Phase 03

Structural and first fix

Everything that ends up buried. Nothing in this phase can be changed cheaply once the plaster is on.

Phase 04

Plaster and dry

Plaster needs time. Building this wait into the plan is the difference between a calm kitchen and a rushed one.

Phase 05

Fit out

The order here matters more than anything else in the room. Flooring is the one variable: it goes down before the units if it runs underneath them, and after the worktop if it butts up to them.

Phase 06

Finish

The short list that decides whether the room feels finished.

General guidance, not professional or legal advice. The sequencing describes common UK practice. Anything involving gas, electrics, structure or asbestos needs a qualified person, and the rules on permission and sign-off differ by country, so check what applies where you live.