Bedroom renovation checklist

The cheapest room to get right and the easiest to redo, so it is the best room to start on.

What goes wrong in a bedroom

  • AvoidLaying the floor before decorating. Painting first is much faster and the cutting-in is neater.
  • AvoidLetting the electrician run cable before the bed position is settled. Bedside sockets in the wrong place are the most annoying cheap mistake in the house.
  • AvoidGetting the wardrobe order wrong. Built-in wardrobes go in before the carpet, freestanding ones after it.
  • AvoidSanding an old ceiling before anyone has checked it. Textured coatings in an older house may contain asbestos, and testing comes before sanding.

Phase 01

Decide before anyone starts

Short list, because a bedroom has fewer irreversible decisions than any other room.

Phase 02

Strip out

Fast, and worth doing thoroughly so the finish has a chance.

Phase 03

First fix and repairs

Everything that goes behind the plaster or the paint.

Phase 04

Plaster, then decorate

Decorating before the floor is the single biggest time saving available in this room.

Phase 05

Fit out and finish

The last day, in the order that avoids damaging fresh work.

General guidance, not professional or legal advice. The sequencing describes common UK practice. Anything involving gas, electrics, structure or asbestos needs a qualified person, and the rules on permission and sign-off differ by country, so check what applies where you live.